Maryland targets 3GW of energy storage by 2033

The Maryland State House where legislation is proposed and enacted. Image: Martin Falbisoner / Wikicommons.

Legislators in the US state of Maryland have voted to approve a bill requiring the deployment of at least 3GW of energy storage by 2033, the latest US state to make such a move.

House Bill 910 was passed by the Maryland General Assembly this week and requires the states’s Public Service Commission (PSC) to establish a ‘Maryland Energy Storage Program’ and set deployment targets.

The targets are a cumulative 750MW by 2027, 1,500MW by 2030 and 3,000MW by 2033, using the delivery year of grid operator PJM which starts on 1 June of the stated year (meaning an ultimate deadline of 31 May 2034). The programme must be presented to the General Assembly by the end of this year and implemented by 1 July 2024.

The 3GW is set in stone and falls at the mid-point of American Clean Power’s (ACP) recommendation of 2.5-3.6GW in a recent study. The way in which to get to that figure is yet to be determined but the Bill outlines two main options.

The first is a ‘system of energy storage credits and market-based incentives designed to developa robust energy storage market in the State and deploy energy storage devices in a cost-effective manner’. That would potentially mean layering on incentives to the federal ones brought in by the Inflation Reduction Act, like New York has done for manufacturing.

The second option is a ‘requirement that investor-owned electric companies install or contract for energy storage devices or contract for energy storage credits from an energy storage project under the Maryland Energy Storage Pilot Program’.

That is the route taken by California, which has in the past few years mandated its load-bearing entities to procure renewable and storage resources. The latest project announcement under these frameworks is an eight-hour lithium-ion project by NextEra Energy Resources, reported today.

But other options may also be explored, with the bill adding that the programme could include ‘any other mechanism or policy that PSC determines is appropriate to achieve the goal of a robust cost-effective energy storage system in the State’.

ACP applauded the passing of the bill, with Moira Cyphers, Eastern Region State Affairs Director, saying: “As storage is critical to meeting our nation’s emissions and energy goals, Maryland’s passage of this energy storage bill signals important progress toward building clean energy capacity.”

The bill follows on from a smaller pilot programme which saw the PSC mandate the state’s four big investor-owned utilities to procure two energy storage projects each, of varying types and uses in 2019.

The four utilities are Potomac Edison, Baltimore Gas and Electric, Delmarva Power and Light and Potomac Electric Power. The PSC has approved all eight projects which total 9MW and 31MWh, which started to come online in late 2022. Smaller utilities have been deploying their own projects too, reported by Energy-Storage.news.

States across the US are now setting energy storage targets to ensure deployments can catch up with new renewable resources. Maryland is the latest to in 2023 after Michigan and New Mexico did the same.

Continue reading

Offtaker discusses NextEra’s eight-hour lithium-ion California BESS project

Clean Power Alliance (CPA) colleagues visiting the site of another BESS project the utility has procured from, Luna. Image: Clean Power Alliance (CPA).

NextEra’s eight-hour energy storage project in California will use lithium-ion technology, but ‘battery chemistry did not play a major role in project evaluation’, offtaker Clean Power Alliance told Energy-Storage.news.

CPA, a community choice aggregator (CCA), last week secured a long-term power purchase agreement (PPA) with NextEra Energy Resources for the offtake of Desert Sands Energy Storage facility in Riverside County, as reported here yesterday.

The deal is part of CPA’s requirements under the California Public Utilities Commission’s Mid-Term Reliability order for load-bearing utilities to procure additional resources by 2026. It is the third eight-hour lithium-ion project to be procured by CCAs as part of those procurements (the first and second were announced in January and March respectively last year).

Responding to Energy-Storage.news’ request for comment after our story was published, CPA confirmed the project’s choice of lithium-ion technology and that it would be a 75MW/600MWh system. It has not yet been decided whether it will use LFP or NMC battery cells, however.

They said that construction on the project is expected to start by 1 December 2025, in time for a June 2026 commercial operation date (COD).

When asked whether other battery chemistries were considered and why lithium-ion was ultimately chosen, the spokesperson said: “The Long-Duration Storage category in the 2022 Midterm Reliability RFO was technology agnostic.”

“Projects were evaluated based on a combination of quantitative and qualitative criteria. Quantitative criteria focus on project performance and economics, while qualitative criteria focus on factors related to environmental stewardship, workforce development, development risk, project location, and impact on Disadvantaged Communities.

“Additionally, commitment to CPA’s Supply Chain Code of Conduct was an important qualitative consideration. Battery chemistry did not play a major role in project evaluation.”

The spokesperson did not comment on Energy-Storage.news‘ suggestion that the long timeframe to construction – more than 2.5 years – will potentially allow for cost reductions for lithium-ion batteries. After a decade of such price falls the price increased in the past two years due to lithium carbonate price spikes.

Haresh Kamath from the Electric Power Research Institute (EPRI), a utility-owned research organisation, previously told Energy-Storage.news he expected lithium-ion to become cost-competitive at 24 hours’ duration by the end of the decade.

Continue reading

Invinity moves to 30-50MWh deployment sizes with UK project, targets 100MWh+ by 2025

Invinity’s system at the Energy Superhub Oxford hybrid project, UK. Image: Invinity Energy Systems.

Invinity Energy Systems will deploy a partially grant-funded 7MW/30MWh vanadium redox flow battery (VRFB) system in the UK as the company scales up its project sizes.

The company has been awarded £11 million (US$13.6 million) by the Department for Energy Security and Net Zero (DESNZ) to deploy the 4.3-hour project at a node on the transmission network, run by National Grid.

It will provide a ‘broad range of services to the grid’, and the funding came from Phase 2 of the Longer Duration Energy Storage (LDES) Demonstration Competition.

The project is Invinity’s largest to-date, taking that title from – and doubling the size of – a recent 15MWh order from Taiwan, and will be the largest grid-scale battery system ever manufactured in the UK and one of the largest in the world, Invinity claimed. It didn’t give a targeted commercial operation date (COD).

It is also claimed the project would be the largest long duration battery asset connected to the UK grid, though this may be a technicality. As Energy-Storage.news recently reported in response to a similar claim by other firms, four-hour-plus projects of 30MWh or larger are already online with more coming in 2023 and 2024.

The project marks the start of the VRFB company more broadly scaling up its project sizes from the high single-digit megawatt-hours today to the 30-50MWh range for the next few years with the potential for over 100MWh in 2025, as explained by VP business development Matthew Walz in an interview at Energy Storage Summit USA last month. The interview was prior to today’s UK grant and project announcement, and was mostly focused on the US market.

“Invinity already has three substantial projects coming online this year. The CEC-funded Viejas Enterprise microgrid project in California at 10 MWh, the Yadlamalka Energy project in Australia is 8 MWh and the Chappice Lake Project by Elemental Energy in Canada at 8.4 MWh. The last two being solar plus storage projects,” Walz said.

“We have talked to people about three-digit MWh sized projects which could be coming online from 2025 onwards but between now and then we expect to be primarily deploying projects in the 30-50MWh range.”

He added that Invinity’s next generation product would deliver larger projects at a higher performance and lower cost with today’s mainly optimised at the shipping container level. The company has “pretty clear pricing and specifications on what that is for 2025 and beyond” he said in response to a question about the flow battery sector’s lack thereof, according to some developers.

Walz also pointed to similar grant funding opportunities for Long Duration Energy Storage (LDES) projects in the US, as well as the country’s investment tax credit (ITC). The recent tailwinds in the US mean Invinity expects the US will be one of if not the largest market for the company.

“The US’ Department of Energy is in the midst of awarding US$330 million in grant funding for non-lithium long duration energy storage projects.  Award notices are expected to be announced in Summer 2023. We believe Invinity’s storage solutions are an excellent fit for the program’s requirements and objectives.”

“We expect to have our product qualify as domestic content by 2025 allowing US project developers to earn the ITC domestic content bonus. We are waiting for the IRS guidance on this, which is not expected until the second quarter of this year.”

LDES technology was a big talking point at the two-day Summit in Austin, Texas. In one panel discussion, New York ISO said that grid operators cannot afford a ‘bubble bursting’ event in the LDES sector with some other panellists drawing a parallel between the technology space today and the ‘dot-com’ internet era of the late 1990s.

VRFB is certainly one of the more long-standing technologies in the LDES sector, invented in the 1980s, with its patent expiring in 2006 and commercial projects operational today around a decade old, possibly older.

Lithium-ion nonetheless continues to sometimes be chosen for 4-8 hour duration energy storage projects. US utility Duke Energy told Energy-Storage.news in August last year that it would still choose the industry incumbent chemistry for a 7.3 hour system if it had to today.

And this week a PPA was signed for the offtake of an eight-hour project in California which the offtaker Clean Power Alliance told Energy-Storage.news will be a lithium-ion system.

Continue reading

ROUNDUP: Fluence in Philippines, Asahi Kasei’s US$100 million VC funds, Leclanché builds LeBlock

One of the BESS projects in Fluence’s buildout for SMC Global Power. Image: Fluence.

News in brief from around the word in energy storage with another edition of the Energy-Storage.news roundup.

Fluence at finish line of 570MW Philippines projects

After Philippines president Ferdinand Marcos Jr celebrated the country’s biggest buildout of battery storage to date, energy storage technology and services provider Fluence has noted the role it played.

As reported by Energy-Storage.news earlier this month, the president attended a ceremonial switch-on event for a grid-scale battery storage installation as it came online for power company SMC Global Power.

SMC Global Power is building 1,000MW/1,000MWh of battery energy storage system (BESS) assets, deploying them at the sites of existing thermal power plants in its portfolio to provide grid-stabilising ancillary services like frequency and voltage regulation.

On the occasion of Marcos’ visit, the company noted that it aimed to have the full 1,000MW of BESS commissioned by the end of this year.

Fluence and fellow energy storage system integrators Wärtsilä and ABB were hired by SMC Global Power to deliver the projects through engineering, procurement and construction (EPC) contracts.

Fluence got the largest share of those awards, responsible for 470MW of the portfolio. Shortly after the presidential visit, the company pointed out that it had completed those projects, which were distributed across 18 sites.

Adding this to the Philippines’ first-ever grid-scale BESS, a 10MW system which Fluence delivered for SMC Global Power at its Masinloc coal power plant a few years ago, the multinational technology group has worked on 570MW completed projects in the country, it said. 

Asahi Kasei to invest US$100 million in carbon neutrality startups

Asahi Kasei, which played a key role in the invention and commercialisation of the lithium-ion battery, has pledged to invest in climate tech including energy storage.

The Japanese company said today that it has established a new “investment framework” to allow it to invest in early-stage startups focused on carbon neutrality and solving environmental issues, through its corporate venture capital (CVC) activities.

Asahi Kasei’s CVC offices have been based in California’s Silicon Valley since 2011, investing in startups and forming joint venture (JV) businesses with them. Launched three years prior to that, the CVC arm has in total invested in 50 startups in the US, Europe, China and Japan.

However, it said its activities to date have come under a brand of ‘Care for people’, advancing areas such as life sciences. These areas, including Internet of Things (IOT) and healthcare, have relatively short runways to commercialisation, whereas climate investments, to come under a banner of ‘Care for Earth’, have much longer-term prospects.

At the same time, climate technologies such as hydrogen and energy storage do not yet have established supply chains in place.

These two dynamics have led to the company launching its new framework for ‘Care for Earth’, with Asahi Kasei pledging to invest US$100 million from now until the end of the 2027 financial year in companies working in fields including energy storage, hydrogen, carbon management and bio-based chemicals.  

Leclanché completes first installation of LeBlock modular BESS

Leclanché has made the first deployment of its modular battery energy storage system (BESS) solution, ‘LeBlock,’ at a microgrid on a Mediterranean island.

The Switzerland-headquartered battery storage technology company said last week that delivery, installation and commissioning have been completed on the project, which features 1.2MW output and 1.6MWh of battery capacity.

While its location has not been disclosed, Leclanché did say that the project was for a Greek transmission system operator (TSO), and that the BESS will maximise energy consumption from an adjacently-installed onsite solar PV array.

LeBlock was launched in May 2021, with an Energy-Storage.news webinar and an exclusive interview with Leclanché VP for system engineering Daniel Fohr and EMEA region sales and business development manager Cyril Carpentier to explain the concepts behind its design.

The solution features 5ft cube-like BatteryBlocks, battery containers that can be slotted together to create different sizes and configurations, with each row of BatteryBlocks plugged into a CombiBlock, which includes cooling, thermal management and energy management system (EMS) and battery management system (BMS) components.

Leclanché’s LeBlock features BatteryBlocks (green stripe) linked together with a CombiBlock (orange stripe). Image: Leclanché.

Energy-Storage.news’ publisher Solar Media will host the 1st Energy Storage Summit Asia, 11-12 July 2023 in Singapore. The event will help give clarity on this nascent, yet quickly growing market, bringing together a community of credible independent generators, policymakers, banks, funds, off-takers and technology providers. For more information, go to the website.

Continue reading

Energy Dome: Turning a greenhouse gas into a cheaper form of energy storage than lithium-ion batteries

Energy Dome’s 2.5MW/4MWh demonstration plant in Sardinia, Italy. Image: Energy Dome

‘CO2 Battery’ startup Energy Dome was only founded in 2020 but has drawn the attention of media and investors alike already.

The company, headquartered in Lombardi, Italy, was launched by CEO Claudio Spadacini to address the need for long-duration energy storage (LDES) at scale. A megawatt-scale commercial demonstrator is already up and running in Sardinia, combining the storage of energy under an inflatable dome that is claimed to be safe, standardised, and crucially, cheap.

Danish energy company Ørsted is exploring the feasibility of a 20MW/200MWh CO2 Battery plant, and at the beginning of this year Energy Dome got €17.5 million (US$18.5 million) in grant and equity financing committed to from the European Union’s European Innovation Council.

Speaking a few weeks ago at the Energy Storage Summit, Energy Dome SVP of strategy, corporate development and investor relations Ben Potter explains the value proposition, why the company thinks it can compete with lithium-ion on cost, and the challenges ahead for Energy Dome and a wave of other long-duration energy storage (LDES) providers.

Energy-Storage.news: Energy Dome’s first large-scale demonstrator, a 2.5MW/4MWh CO2 Battery system, went online in mid-2022, following the close of a US$11 million Series A funding round. Our readers may already be familiar with that from Energy-Storage.news’ coverage, but can you introduce Energy Dome in your own words?

Ben Potter, Energy Dome: We are long-duration energy storage-focused and long duration for us is 8, 10 to 24 hours. We can do under 8 hours, we can do beyond 24 hours, but our sweet spot is energy shifting and between 8 to 24 hours.

Our tech is based on a thermodynamic transformation of CO2 in a closed loop process, essentially a thermomechanical play. We take gas CO2, compress it adiabatically, store the heat in a thermal energy storage device, and then liquefy the CO2 as a high energy density fluid.

Then to dispatch the power we invert that process: evaporate the CO2, recover the heat from the thermal energy storage device, and then expand that hot CO2 under pressure through a turbo expander which drives a generator. So the power goes back to the grid and the CO2 goes back to the dome.

To store, we liquefy the CO2, and we store the heat. Then to dispatch, we evaporate the CO2 and expand it heated up through a turbine, essentially.

ESN: A closed loop process is something a lot of energy technologies look to achieve. But why use CO2?

Ben Potter: CO2 has a critical state of 31°C. So that means that if you put it under pressure at ambient temperature, it liquefies. So as a liquid, it’s very high density fluid, but because it liquifies at ambient temperature, you don’t need cryogenic equipment, and you don’t have efficiency losses. It’s a really, really good fluid to store energy. It’s got the right molecular weight.

The reason why Claudio (Spadacini, founder and CEO) came up with the idea for our CO2 Battery process plant is because of his background working in various different industries.

In particular, he developed a brand new organic Rankine cycle turbine in a previous venture called Exergy. With an organic Rankine cycle plant, you need to choose the working fluid. He knew the thermodynamics well, and he was familiar with CO2 and the properties of it, and other gases.

Secondly, he also founded a biogas company. So he was familiar with the domes that were used to store CO2 as a gas inside. And he also worked in Korea in turbo machinery. So he knew turbines, compressors, all of that process engineering.

So it was just basically integrating a whole bunch of experiences. He was looking at the long-duration energy storage market and looking at what other technologies were doing, in particular, compressed air energy storage and liquid air energy storage. And the principles are fantastic on that.

It makes sense to use CO2 as a working fluid. The key thing is how you store it on the low pressure side. And because he worked on biogas, he knew that we could just use the biogas domes. Then he added in a thermal energy storage kicker, essentially, to basically boost the round trip efficiency.

It uses off the shelf components, so it leverages existing supply chains.

‘Standardisation is key’

ESN: It seems to be quite important for other LDES tech companies to use components or processes from other already commercialised industries.

BP: All of the components come from the existing power industry and existing oil and gas industry, essentially the ‘dumb’ components, which have been in the market since the 1960s, with a fancy process over it.

So the compressors are integrally-geared six-stage compressors, which are used in the oil and gas industry, the turbine’s very similar to a medium pressure steam turbine, heat exchangers are used in oil and gas industry process industries, the dome is from the biogas industry, and then we’ve just got lots of pressure vessels.

So it’s basically just carbon, steel, water and CO2. And given that we’re getting it from Tier 1 OEMs, we buy the components from them, and they give us performance guarantees on their balance sheets. So we’re extremely confident in the capex and the performance of it. What that translates into is very scalable supply chains which are ready to go, and we don’t have to build a factory to go to market, we just get an order from customers and we place back-to-back orders from our suppliers.

ESN: Can you give us an idea of what sort of cost you’re able to achieve, making the CO2 Battery technology in this way?

BP: What that translates into is a CapEx, – for a 10-hour system which is our first of a kind product in the market, 20MW by 10 hours (200MWh) – that is under 50% of a 4-hour lithium-ion project capex, EPC-installed, down to medium voltage with our margin. So we are pricing at EU220 per kWh with EPC, with margin.

The performance of the system is independent of ambient temperature, meaning that you put it in Alaska and you put it in Texas and you still get 75% roundtrip efficiency. That shows in an identical layout all the way down to the nuts and bolts, everywhere in the world.

ESN: So it’s both standardised and replicable? Those sound like words investors like to hear…

BP: Standardisation is the key to industrialising energy storage.

The way the wind energy industry got the levelised cost of energy (LCOE) down in part was due to standardising a three-blade wind turbine. [Manufacturers like] GE, Vestas, Siemens Gamesa, standardised that and then contract manufacture the components, the steel towers, the gearboxes, etc.

We’ve got an identical business model. The standardisation basically means every single time we’re ordering an identical unit, so we get the supply chain economies of scale. That price I gave you was for our first of a kind, but we believe we can get CapEx down by 44% with 30 to 50 identical units. And we’ve confirmed this with our suppliers.

Image: Energy Dome

ESN: One limitation to where you can put them might be the footprint in terms of the dome. And, I think it’s fairly accepted that we will need a diversity of energy storage resources. So maybe Energy Dome isn’t saying we need this technology for everywhere. So how does that kind of stack up in terms of the footprint and where you can deploy the CO2 Battery?

BP: We can be a standalone energy storage asset, we can be co-located with renewables or we can be behind-the-meter.

To co-locate with renewables, solar plus a CO2 Battery, that’s our sweet spot, that works incredibly well.

If you’re going to build a utility-scale solar farm, we would occupy about 6% of the land of that solar farm to make it completely renewable baseload. Because we can store energy efficiently, we’re wasting less land, so we’re wasting less renewables essentially to charge it and discharge it. If you’re purely looking at the metric of how much land we require to store, just the storage part, we store about 4-5kWh per square meter.

That is less than lithium-ion, so obviously, we do require land, but we need to deploy a huge amount of solar and wind, and you can’t deploy that without long-duration energy storage. The key thing is to make the combination of that as land efficient as possible.

The limitations we’ll find will be in behind-the-meter [applications]. If you want to decarbonise a cement plant, a refinery, a petrochemical plant, other areas, we can do that. But if it’s behind-the-meter, and we’re in a very land scarce place, that’d be tricky. So that use case would be limited.

On the permitting side, the material’s identical to a tennis bubble. It’s just an inflatable structure: in coal yards, they use them to cover coal and biogas applications, it’s not a fixed structure with steel. If we need to remove it, we just turn the fans off, pack it away. The authorities when they see that, they’re relieved, because it’s not a fixed structure, and it’s not this huge eyesore which will be there permanently. So that helps a lot.

ESN: Is there anything risky or hazardous about using CO2 as a storage medium?

BP: We use 2,000 metric tonnes of CO2 per 100MWh. That’s a low volume of CO2. We’ve done dispersion modeling and are very comfortable with the analysis.

Worst case scenario, if there’s a leak, let’s say there’s a hurricane, the domes will withstand the speed of the hurricane, but if debris comes in and you lose the CO2, in that case, now the wind basically disperses it.

ESN: In terms of your conversations with investors and corporates, what are some of the frequently asked questions in terms of the sort of challenges that Energy Dome faces to commercialise, perhaps in common with other LDES companies, or that are unique to Energy Dome?

BP: The challenge at the moment is the market offtake side. So essentially, our business models can work in a very similar way to wind turbines, in terms of how we go to market, and our [intended] customer is an independent power producer (IPP) or utility or heavy energy user. We want to supply them the technology for them to make it bankable, especially the IPPs. They’re looking for the market offtake side to be solved.

So they can basically charge and discharge and trade, but from a project finance perspective, often people want the offtake secured in the long run rather than [take] spot merchant risk.

In terms of the new industry and prodding it in the right direction, the biggest challenge is enough countries putting in market mechanisms, with fixed remuneration, over 20-plus years for the developer or the IPP, or utility of that project.

If enough of those come into the market, this is going to go mainstream much quicker, because it basically takes the market risk equation out for our customers. And we’ve seen that in the US, particularly in California and Arizona and Nevada, we’ve seen the tolling capacity tenders coming out. There’s one coming in Italy as well.

Basically, you need to set a long-duration energy storage target, and if those mechanisms are used, that’ll be the market. That’s our biggest challenge at the moment.

Continue reading

UK’s Gresham House sees ‘strong growth in earnings’ from high ancillary service prices

Glassenbury, one of the earlier BESS projects added to Gresham House’s portfolio. Image: Gresham House.

Delays in the growth of Britain’s battery energy storage system (BESS) sector helped boost Gresham House Energy Storage Fund’s (GRID) portfolio performance, resulting in a “strong growth in earnings” in 2022.

In its financial earnings results ending 31 December 2022, London Stock Exchange-listed investment fund GRID disclosed that the earnings before interest, taxes, depreciation, and amortisation (EBITDA) for its underlying portfolio grew by 23.2% to £48.8 million (US$60.67 million).

It said that the strong performance was as a result of undersupply of BESS capacity in key frequency response services, which kept prices high. 

The company also experienced an increase in its net asset value (NAV) to 155.51p (US$1.93) per share – a 33.1% increase from the 31 December 2021 NAV valued at 116.86p per share.

Gresham House Energy Storage Fund reported that the greatest challenged faced by the construction activities within its investment portfolio were longer lead times and complications relating to obtaining grid connections for projects.

Despite the revenue increase in 2022, GRID noted that it is yet to experience potential cost decreases – in relation to insurance for example – as forecast.

“In 2022 GRID further built on its strong track record and delivered significant growth in earnings, operational capacity and NAV per share, while maintaining a fully covered dividend as projects became operational. Following GRID’s strong trajectory in 2022, the Company has set its ambitions higher going into 2023,” said John Leggate CBE, Chair of Gresham House Energy Storage Fund plc.

“We are exceptionally well-positioned to capitalise on the exciting battery energy storage opportunities ahead of us in the UK and our targeted international markets.”

To read the full version of this story, visit Solar Power Portal.

Continue reading

Malaysia government minister welcomes country’s first ‘homegrown’ BESS solution

The launch of MYBESS, with MITI’s minister Aziz in the centre. Image: Citaglobal Genetec BESS.

The first locally-produced battery energy storage system (BESS) product in Malaysia will support the energy transition and boost competitiveness in high tech industry sectors, a government minister has said.

The country’s Minister of International Trade and Industry, Zafrul Tengku Aziz, was in attendance yesterday as MYBESS, an end-to-end solution for renewable energy storage, was launched.

The two Malaysian companies behind it – engineering, energy and manufacturing conglomerate Citaglobal and industrial automation group Genetec Technology – showcased the 1MW prototype MYBESS at a Genetec production plant in the town of Bangi, just outside the capital Kuala Lumpur.

Developed and produced through a special purpose vehicle (SPV) called Citaglobal Genetec BESS, the prototype is fully operational since a pilot project began in December last year, helping optimise the Genetec plant’s energy use.

Their collaboration was formalised last October, with the parties agreeing to develop battery management system (BMS) and energy management system (EMS) technologies, aiming at maximising the large-scale and large capacity storage of energy. At the same time they have developed a product that is portable and capable of deployment in various scenarios, which could help Malaysia with rural electrification efforts, the companies claimed.

Malaysia has set a net zero deadline of 2050, and through the government’s New Investment Policy, will strengthen its ESG adoption, and rethinking “how we generate, distribute, store, supply and consume energy,” is a key part of that, minister Aziz said.

“To this end, the development of Malaysia’s homegrown MYBESS, by Citaglobal Genetec BESS, is not only a step in the right direction in support of Malaysia’s future (renewable) energy security, but also an important opportunity to begin positioning Malaysia in high-technology industries and higher in the global value chain,” Aziz said, citing that the Ministry of International Trade and Industry (MITI) will take “bold steps” to enhance Malaysia’s “industrial ecosystem,” when it launches a national New Industrial Master Plan 2030, later this year.

The minister’s words somewhat echo the words of Philippine president Ferdinand Marcos Jr, who recently said it is “vital” for Malaysia’s neighbour to incorporate energy storage into the framework of its energy sector. According to various sources Energy-Storage.news has spoken to, including DNV’s energy storage lead for the APAC region, George Garabandic, Southeast Asia has seen an uptick in investments into energy storage over the past couple of years.

Energy-Storage.news’ publisher Solar Media will host the 1st Energy Storage Summit Asia, 11-12 July 2023 in Singapore. The event will help give clarity on this nascent, yet quickly growing market, bringing together a community of credible independent generators, policymakers, banks, funds, off-takers and technology providers. For more information, go to the website.

Continue reading

California utility signs PPA with NextEra for eight-hour energy storage project

A battery storage site in Indiana deployed by NextEra. Image: NextEra Energy Resources.

California utility Clean Power Alliance has inked a 15-year PPA with NextEra Energy Resources for an eight-hour duration energy storage project.

Clean Power Alliance (CPA) announced the long-term power purchase agreement (PPA) with energy giant NextEra Energy’s clean power arm last week (7 April). The PPA secures the offtake from NextEra’s 75MW, long-duration Desert Sands Energy Storage facility in Riverside County, California, starting in June 2026.

A media statement said that the agreement marks CPA’s “…first executed contract incorporating eight-hour storage capabilities. CPA’s many other battery storage projects incorporate four-hour battery technologies. Compared to a four-hour battery of the same size, an eight-hour battery can discharge twice as much energy.”

It did not reveal the technology used or energy storage capacity but the stated duration and power would make it a 600MWh system. The California ISO’s (CAISO) Resource Adequacy programme, through which utilities secure capacity from generating units, only requires a four-hour duration for energy storage.

Energy-Storage.news has asked CPA for more details and will update this article in due course.

CPA is one of California’s many CCAs, smaller community-owned utilities which provide local communities an alternative to the state’s big three investor-owned utilities PG&E, SDG&E and SCE. This is its fourth battery energy storage system (BESS) PPA deal.

It was in the headlines late last year when its third, a 100MW/400MWh project, Luna came online after a ‘landmark’ debt finance deal was secured.

The PPA deals are being struck after the California Public Utilities Commission (CPUC) ordered load-serving entities to procure new resources between 2023 and 2026, to address so-called mid-term reliability concerns. As part of its share, CPA needs to procure some 59MW of long-duration energy storage which this PPA satisfies entirely.

Continue reading

New standalone ITC incentivising US developers to overbuild projects

Project site of the Madero and Ignacio BESS assets in South Texas. Developer Eolian claimed they are the first to utilise the ITC for standalone storage. Image: Wärtsilä

The new investment tax credit (ITC) for standalone energy storage means some US developers are opting to overbuild instead of augment later, system integrators told Energy-Storage.news.

The standalone ITC, brought in as part of the Inflation Reduction Act and effective as of 1 January this year, has meant a significant uptick in developer interest in the US grid-scale energy storage market.

New entrants are coming into a market where existing participants are increasingly having to think about augmenting existing systems as well as deploying new ones, as Energy-Storage.news recently wrote in an interview with EPC firm Burns & McDonnell.

The ITC means that developers are increasingly opting to invest more now and overbuild rather than augment several years down the line as the systems’ batteries degrade, executives from system integrators Powin and Wärtsilä told Energy-Storage.news whilst attending Energy Storage Summit USA last month. A third, LS Energy Solutions, gave a different viewpoint.

“The IRA incentivises Capex spending now to get the tax credit so we are seeing customers overbuild, like deploying 120MW with a 100MW interconnection,” said Kate Sherwood, director of energy storage North America at Wärtsilä, though emphasised some were still opting to avoid the current high costs of lithium-ion batteries and augment later.

“Others are taking the bet that batteries will go down in cost so they’ll build 100MW and augment in 3-5 years.”

Anthony Carroll, president of Powin, echoed these comments: “One very nice thing about the IRA is that we’re getting many more customers augmenting at the initial part of the lifetime of the project and not seven years from now. The ITC means that people are investing more upfront in those batteries whereas before people were trying to divert costs as much as they could. We’re seeing both approaches to augmentation play out.”

“Augmenting in 7-10 years means leaving space for those new ones, so it’s less efficient in its design, and also the battery and inverter technology will change. I can guarantee you that the inverter technology in 7-10 years from now is not going to be what it is today.”

He added that he nonetheless expected augmentation to become a substantial market in and of itself in the coming years, with companies specialising purely in adding capacity to existing projects.

Ravi Manghani, director of strategy and market analytics at LS Energy Solutions, did not agree that this move to overbuilding at deployment rather than augmenting later was a given. His firm released its utility-scale product in late 2021.

“Yes, that (overbuilding) would be the first approach. But we still don’t know how the IRA will rule on augmentation specifically. In theory, you could pay upfront for augmentation further down the line and still take advantage of the ITC. It’s still not clear what the IRS (Internal Revenue Service) will decide on and what kind of guidance they’ll provide on sizing and oversizing and augmentation.”

Updated IRS guidance on various aspects of the new ITC mechanisms brought in by the Inflation Reduction Act is expected during the current quarter (Q2).

Continue reading

Solar Developer Acquiring 1.5 GW of Huasun HJT Modules

Anhui Huasun Energy Co. Ltd. has signed a cooperation agreement with INERCOM Ltd., a European EPC company, for the supply of at least 1.5 GW of Himalaya series ultra-high-efficiency HJT modules by the end of 2025.

Huasun first worked with INERCOM in 2021, supplying 86 MW of HJT solar modules to its utility solar project in southern Bulgaria. According to the supply plan, by the end of 2023, Huasun will deliver more than 500 MW of modules for INERCOM.

“We choose Huasun as the exclusive supplier of HJT modules because they have provided a great guarantee in terms of product quality, technical performance and delivery capabilities,” says Malina Varbakova, heads of INERCOM. “We are very happy to build a long relationship with Huasun and hope both of us can keep strengthening connections, supporting each other and exploring the international market together.”

“INERCOM has been deeply involved in the Bulgarian market for decades and has participated in the development and construction of photovoltaic projects in many regions,” adds Dan Zhou, CEO of Huasun. “It is the first company that used HJT modules on a large scale at an early stage in Europe, which indicates that HJT has very broad prospects and significant value in Europe.”

Continue reading