Hecate Grid signs utility contract, gets local approval for 1,200MWh California BESS project

The Hecate Grid Johanna 80MWh BESS in Santa Ana, California. Image: Ingeteam.

Hecate Grid has progressed a 300MW/1,200MWh battery storage project in California, US, signing off-take contracts for its stored energy and gaining a key local authority approval.

The independent power producer (IPP) said last week that it has achieved what it described as two key milestones in the development of Humidor Battery Energy Storage System (BESS) Project, in Los Angeles County, California.

That included contracts signed with two California energy suppliers, the major investor-owned utility (IOU) Southern California Edison (SCE) and with MCE, one of the state’s community choice aggregator (CCA) groups.

CCAs are like non-profit utility companies which allow customers to choose where their energy comes from, with many electing to offer renewable energy-rich tariffs.

The contracts are for resource adequacy (RA), the main mechanism through which load-serving entities in California have to ensure they have sufficient energy resources available. RA contracts are typically long-term, typically providing secure revenues to BESS asset owners and investors over terms in excess of 10 years.

RA is particularly important in helping utilities and the main California grid operator CAISO ride out peak demand periods and over four-hour windows throughout the day and night. Contracting for RA has therefore led to a proliferation of four-hour duration battery projects in California.

Hecate Grid’s Humidor project will similarly charge up from the grid during times of surplus renewable energy and at off-peak times when power prices are cheaper and then discharge into the grid when demand peaks.

As widely noted, battery storage is playing an increasingly major role on the CAISO grid in managing the crunches in supply and demand, especially from the 4pm to 9pm daily window when solar PV generation tails off and evening demand for power from consumers kicks off. That role was brought to widespread attention during the August heatwaves, when there was serious risk of CAISO having to enact rolling outages – a risk which was eventually averted. More than 3GW of battery storage was discharging to the grid at certain times during evening peaks in that heatwave.

Hecate Grid said it has also received site plan approval from LA County officials for Humidor. It expects to have the project commissioned and in commercial operation in H1 2024.  

The IPP was started up by US renewable energy developer Hecate Energy as a joint venture (JV) with investor InfraRed Capital Partners and is now a separate entity, having been spun out.

The company brought online Johanna Energy Storage System, a 20MW/80MWh standalone BESS project in Santa Ana, California, in late 2021. Johanna is serving as a pilot project for SCE to assess how battery storage can help the utility match its electricity supply and demand, which are increasingly fluctuating with the addition of variable renewable energy to the CAISO energy mix.

Hecate Grid is also now building a further three California BESS projects totalling 105MW/210MWh in Riverside County and aims to issue Notices to Proceed on a portfolio of 750MW/1,500MWh of battery projects in Texas’ ERCOT market later this year, it claimed.

“Energy storage packs a one-two punch. It supports wide scale deployment of renewable energy while mitigating energy costs for consumers,” Hecate Grid VP of business development Gabe Wapner said.

2.15GWh buildout in SCE territory nears completion

In related news, the construction partner contracted to deliver 2.15GWh of battery storage projects in Southern California Edison (SCE) service territory for developer Ameresco said work is nearing completion.

BEI Construction said the three-site project, on which construction began in April 2022, should be finished by the end of this year.

One of the biggest battery storage buildouts ever contracted, SCE signed up Ameresco for the total 537.5MW/2,150MWh of projects in Southern California to help it manage its peak demand.

The contracts had originally been signed and then announced in 2021 on the basis that they would be delivered before this August, helping to mitigate the fierce California summer peak in demand.

However, in April Ameresco said it was encountering circumstances amounting to force majeure events that would prevent it from meeting the deadline, citing factors including COVID19-impacted shipping and supply chains and new rules in China on the safe import of batteries.

By the beginning of August, when Ameresco announced its most recent financial results, CEO George Sakellaris said project teams were “working around the clock” to get them finished as soon as possible, by the end of the year.

Continue reading

Quinbrook’s UK BESS optimiser Habitat Energy furthers US expansion with Texas deals

Habitat’s optimised assets include the hybrid lithium-vanadium BESS at the Energy Superhub project in Oxford, England (pictured). Image: Pivot Power.

UK-based Habitat Energy has expanded into the US power market with plans to optimise a portfolio of 60MW of battery energy storage system (BESS) assets.

With a partnership signed with Glidepath Power Solutions, Habitat will optimise the company’s 10MW/10MWh Prospect battery storage project in West Columbia, Texas. Habitat will also optimise Glidepath’s 50MW Byrd Ranch storage project in Sweeny, Texas.

The optimisation of the projects will be achieved via the use of Habitat’s trading platform, with full route-to-market capabilities for both the wholesale and balancing markets. It is based on the company’s proprietary software PowerIQ, which combines algorithmic forecasting and AI.

Habitat will aim to increase its overseas portfolio building on its over 700MW of storage capacity in the UK.

For the US market, Habitat will not only focus on battery storage optimisation, but also on renewables and hybrid facilities.

The firm stated that it recognises the substantial revenue opportunity that sophisticated AI optimisation can deliver by trading across Day Ahead and Real Time markets in addition to dynamically analysing hub and node price differentials in real time.

Habitat and Glidepath are both portfolio companies of Quinbrook Infrastructure Partners.

This is the latest development in Habitat’s expansion of its services into North America. In May 2021, the firm agreed a partnership with Canadian Solar, one of the world’s largest solar technology and renewable energy companies.

As reported at the time, the partnership would see the Ontario based company offer Habitat enhanced technology solutions for developers and owners of battery storage assets across its operations, enabling them to capture additional revenue from trading optimisation.

To read the full version of this story, visit Solar Media’s UK energy transition site, Current±.

Continue reading

Fluence’s Cube ‘surpasses’ UL9540A fire testing requirements

Fluence Cube units at one of the company’s Gridstack utility-scale BESS projects. Image: Fluence.

Large-scale fire testing of Fluence’s battery storage solution showed that thermal runaway in one ‘Cube’ would not spread fire to surrounding units.

The system integrator said last week that testing of its products against UL9540A – considered one of the main standards for energy storage safety – has been successfully completed.

Fluence’s sixth generation of products, launched in 2020 and currently used in all its projects globally, were put through the tests, assessing their ability to limit the spread of potential fire to subsystems without thermal runaway propagating from one to the next.

Fluence alluded to the Cube, which is the hardware building block of its Gridstack systems for large-scale utility use, having surpassed the safety testing requirements in independent testing conducted by international certification group DNV.

UL9540A doesn’t have a specific pass or fail criteria as such, but the tests, formulated in partnership with the US National Fire Protection Association (NFPA) are widely considered indicative of system and component adequacy for safety, and by extension bankability for customers looking to procure large-scale battery storage.

Increasing numbers of technology providers are publicly sharing their results, with UL itself hosting some – though not all – providers’ results on its own website.

“The results of Fluence’s large-scale fire test show that, in the unlikely event a Cube goes into thermal runaway, the product is designed to contain extreme internal battery failures to a single Cube and not spread through an energy storage system,” DNV business development leader Martin Plass said.

Plass described the test as “particularly impressive,” because full-scale fire in the originated Cube didn’t cause internal temperatures in surrounding units to reach levels high enough to cause thermal runaway, “even without intervention from external emergency personnel”.

That means if one Cube has problems like an internal short circuit caused by mechanical damage or even defective cells, the rest of the battery storage system can be restored to full operation safely, Fluence claimed.

Fire safety: a key priority for integrators and customers alike

Safety is of course a major focus for the battery storage industry, with several industry sources telling Energy-Storage.news at the Electrical Energy Storage Europe (ees Europe) event earlier this year that there is no bigger priority for its customers.

While fires are rare, there have been a number that have caused concern, and anecdotally it seems local community reluctance to host new utility-scale battery storage facilities focuses on the safety aspect of lithium-ion batteries.

Most people are willing to have lithium batteries in their pockets in their cellphones, or even in their ears in their earbuds and headphones, but nonetheless numerous newspaper reports emerge from places like the UK – where a 20MW battery energy storage system (BESS) burned out in 2020 – of groups of residents opposing larger scale systems in their local area.

One fire expert told Energy-Storage.news earlier this year that although fire safety is and should remain of utmost importance, often the general public and even academics unconnected with the industry are unaware that, for example, failures in large-scale energy storage are unlikely to cause the sort of explosive events that one high profile academic research report warned of.

Paul Rogers, a senior firefighter and energy storage safety subject matter expert at Energy Safety Response Group (ESRG), described the authors of that report as lacking understanding of what happens when failures occur at system level, in an interview published at the beginning of this year in our journal PV Tech Power.

Meanwhile, Paul Hayes, general manager of American Fire Technologies and a witness to Fluence’s testing, said that Fluence had taken “a significant step forward by performing this full large-scale installation-level fire and explosion test”.

“Few companies understand how energy storage systems will perform under a large-scale failure and how to help protect first responders during such an event,” Hayes said.

“The test did not result in a deflagration event and, even with a fully engaged Cube, the failure was limited to one Cube with no propagation between containers at distances below code requirements. This test will help define safety standards moving forward.”

Continue reading

Goldbeck Solar Acquires EPC Business of GP Joule for North American Growth

Ove Petersen, CEO of GP Joule, and Joachim Goldbeck, CEO Goldbeck Solar Group

The Goldbeck Solar Group has acquired the North American PV-EPC business unit of GP Joule Group and is now the sole shareholder of the two North American companies: GP Joule PV Canada Corp. and GP Joule PV USA Inc. With this acquisition, GOLDBECK SOLAR is strengthening its position in the Americas, having existing operations in Chile and Mexico.

The purchase includes the acquisition of the entire GP Joule EPC NA team as well as the use of the local brand for a limited period.

“Our new local team and their expertise are the basis for this strategic step. They understand the culture and the market specifics,” says Joachim Goldbeck, CEO of Goldbeck Solar Group. “With our new colleagues, we have a strong foundation to master the opportunities and challenges of the North American market. The cultural fit of the companies was a fundamental criterion, and we are now looking forward to growing the business together in Canada and the USA.”

“This comes at a perfect time,” states David Pichard, CEO of GP Joule EPC NA. “Over the last 10 years, we have grown exponentially a team delivering world class assets in the utility scale market. Becoming part of the Goldbeck Solar family not only brings immediate synergies in systems and supply chain but also accelerates our expansion in operations and maintenance services to continue providing the best value to our clients”.

“We are convinced that we have found the right partner and buyer for our companies in North America in Goldbeck Solar,” adds Ove Petersen, co-founder and CEO of GP Joule. “We are placing our EPC business in Canada and the USA, which has developed excellently in recent years, in good hands and can focus even more strongly on our growth in Germany and Europe.”

Continue reading

Long duration and multi-day storage tech will allow California to put surplus renewable energy to good use

California made a ‘smart choice’ to invest in low-cost renewables, now it’s all about how to best use those assets. Image: Ameresco.

California is pursuing some of the world’s most aggressive renewable energy and decarbonisation pathways. Those hugely positive steps forward however, present some key challenges that energy storage can solve, write the team from iron-air long-duration battery startup Form Energy.

To rapidly decarbonise its electric grid, California made a smart strategic choice: build gigawatts of renewable energy – the cheapest source of electricity available globally – so the state can wean itself from more expensive and polluting fossil-fueled power plants.

From 2010 to 2020, California went from producing 3.4% to almost 22.7% of its energy from solar and wind. It plans to keep building on that momentum, and anticipates building an additional 16.9 GW of solar and 8.2 GW of wind by 2030 to meet energy demand and avoid blackouts during multi-day heatwaves such as the one the state is currently experiencing.

This capacity isn’t always needed, leading to surplus energy that is curtailed, or shut off, during milder shoulder months when electricity demand is lower.

In a world without access to low-cost, long-duration energy storage, the smart investment for California customers is to just keep building more renewables to meet peak demand and avoid burning fossil fuels during expensive summer months.

But at a certain point (spoiler alert: we’re at that point), all that excess energy produced during periods of lower demand becomes an opportunity for the state.

Why are we convinced this moment has arrived? First, renewable energy curtailment is growing faster and persisting for longer periods than expected – at times persisting over multiple days. Second, new classes of low-cost, long-duration (defined here as greater than eight hours) and multi-day (defined here as greater than 24 hours) energy storage are entering the market.

These technologies are poised to deliver long-term benefits to Californians including grid reliability and resiliency, firmed renewables over any weather event or season, improved local air quality, job creation, and local economic development.

Opportunities to store hours to days of excess renewable energy

To understand the hour-to-hour dynamics of renewable energy curtailment, Form Energy examined data from the California Independent System Operator (CAISO) detailing the amount of renewable energy curtailed in California between May 1, 2014, and May 31, 2022.

The results point to the increasing opportunity for long-duration and multi-day storage to help integrate the state’s renewable energy resources.

Figure 1 below plots individual curtailment events over the eight-year period for which data are available and shows the amount of energy curtailed during each event. The size of each bubble represents the duration of the curtailment event.

Since 2014, the average duration of continuous renewable energy curtailment in California has increased from 2.5 hours to 9.5 hours. Many of these curtailment events span multiple days, with the longest event being 71 hours in duration.

The amount of renewable energy curtailed is growing rapidly; thus far in 2022, California has curtailed more than 1,860 gigawatt-hours of wind and solar, which is enough to power more than 200,000 homes for a year. Curtailment during multi-day events specifically totaled more than 110 gigawatt-hours, up more than 37 times since 2014.

Figure 1: Clean energy curtailments.

Storing excess renewable energy for when it’s needed most

During these curtailment periods, energy storage systems at the right locations can store this excess renewable energy at low cost, or even zero cost when electricity prices turn negative during periods of oversupply.

Long-duration and multi-day storage can then use this low cost excess clean energy to manage California’s demand ramps, provide power during net demand peaks, and, in the case of multi-day storage, provide reliability over multi-day lulls in renewable generation.

The first day-to-day use for this excess clean energy is to help solve California’s much discussed “duck curve” – the drop off in net electricity demand during solar production peaks followed by a rapid increase in net electricity demand as the sun sets.

If long-duration storage capacity had been available to charge with the curtailed energy shown in Figure 1 and discharge that energy during peak demand periods, California could have saved more than US$129 million since 2014 and avoided roughly 1.1 million metric tons of carbon dioxide emissions1.

The second major use case for excess clean energy is to fill energy supply during renewable energy lulls. These periods of low intermittent generation are the flip side of the renewable energy curtailment coin.

Form Energy’s analysis of 35 years of solar and wind profiles used in the California Public Utilities’ Commission’s Integrated Resource Planning Process identified 138 instances of multi-day renewable energy lulls (where a lull is defined as any period in which combined wind and solar output is more than 25% below average).

These multi-day renewable lulls pose the greatest reliability threat to deeply decarbonised grids. Today’s commercial battery technologies can economically store up to roughly eight or twelve hours of energy, meaning that they run out of juice during cloudy, calm periods of low renewable generation when they can’t recharge from day to day.

As a result, clean technologies capable of delivering energy over multiple days are critical for ensuring low-cost, clean, reliable power.

Without such technologies, grid planners will need to build vastly more renewable energy than the grid needs to meet typical energy demand and they may also need to keep fossil-fueled resources online, at high cost to customers.

Modeling of a zero-carbon grid in California in 2045 shows how this excess clean energy can be used to support grid reliability during one such lull.

Figure 2 below, taken from the preliminary results of E3 and Form Energy’s assessment of the ability of long-duration storage to help meet California’s energy goals, shows how lower solar output during a cloudy fall week makes it impossible to charge shorter-duration lithium-ion batteries such that they can’t dispatch sufficient energy to meet demand in the evening hours. Instead, multi-day storage steps in to fill this gap, serving California load cleanly and reliably when it is most needed.

Figure 2: Example dispatch during multi-day renewable lull in a portfolio with multi-day storage.

With the frequency, magnitude, and duration of renewable energy curtailment events increasing in California, the opportunity for novel long-duration and multi-day storage technologies to deliver value to California customers has arrived.

Seizing the opportunity

The value of long-duration and multi-day storage technologies to the electric grid will only increase over time as California’s decarbonisation goals become more stringent and the state needs to call on firm zero carbon resources during periods of low renewable output, extreme heat, and other stress conditions.

The state’s recent heatwave led to requests for residents and businesses to keep electricity demand low for nearly a week, underscoring the emerging multi-day weather challenges the state is facing.

Fortunately, the state has already made notable strides toward bringing long-duration and multi-day storage technologies to market. In a first among states, California approved US$126 million in incentives to demonstrate new long-duration storage technologies.

Scaling these nascent technologies requires utilities to begin factoring them into resource planning, which presents a specific modeling challenge that must be addressed. Capturing the hour-to-hour operational dynamics of these resources is the key to understanding their value, which is most apparent during multi-day periods of excess energy and energy scarcity.

Current industry-standard models only capture grid dynamics during a small number of “representative” days or weeks per year, and thus understate the value that multi-day storage can provide to the grid.

However, emerging modeling tools and techniques make it possible to consider the full range of likely grid extremes and to represent the economics of resources that can shift energy across days and seasons. The combination of new long-duration energy storage technologies and better grid planning tools makes it possible to build an electric grid for California that is more reliable, cleaner, and increasingly cost effective.

Note1: Preliminary results from an ongoing Energy and Environmental Economics, Inc. and Form Energy study identified a substantial opportunity for long-duration storage in a zero carbon California grid. The capacity-weighted average round trip efficiency for the long-duration storage resources identified in this study was roughly 39.4%.

Form calculated the dollar and emissions savings numbers by multiplying the total curtailment during events of 8 hours or more (6,809,126 MWh) by the weighted average round trip efficiency (39.4%) and either the on-peak energy prices between 2014 and 2022 (for the monetary value calculation or the natural gas emissions factor (408 kg CO2/MWh) (for the avoided emissions calculation). Average on-peak energy prices for CAISO were taken from S&P Market Intelligence. The natural gas emissions factor was taken from the U.S. Environmental Protection Agency.

About the Authors

Form Energy is a US-based energy storage technology and manufacturing company developing and commercialising a pioneering iron-air battery capable of storing electricity for 100 hours at system costs competitive with legacy power plants.

This piece was written by Form’s Scott Burger, senior manager of analytics, Jason Houck, senior manager for policy & regulatory affairs, Andea Scott, summer strategy & market development analyst and Rachel Wilson, manager of strategy & market development analytics.

Continue reading

Array Debuts Utility-Scale Solar Tracker Systems for Challenging Terrains

Array Technologies Inc., a provider of utility-scale solar tracker technology, is launching its two newest product offerings: Array OmniTrack and Array STI H250. The U.S. launch of the two products expands Array’s existing line of DuraTrack products.

The three tracker product lines address varying customer requirements and the changing needs of the utility-scale solar industry and meet the IRA’s domestic sourcing content requirements.

“The addition of OmniTrack and STI H250 to our continuously evolving product portfolio will help our U.S. customers to better address the unique challenges of their sites. Having a broader offering for our customers helps bring more clean energy to the market faster, advancing the clean energy transition,” says Array CEO Kevin Hostetler. “Array’s global reach, combined with locally-focused sourcing solutions, enhances our ability to deliver the best utility-scale solar solutions to our customers around the world.”

Array OmniTrack, the newest tracking solution to the Array portfolio, is specially designed for customers developing project sites on uneven and challenging terrain. Array’s OmniTrack terrain-following solution mitigates challenges associated with projects on undulating terrain while reducing costs and schedules by enabling less complex site preparation and design.

Following Array’s acquisition of STI Norland in early 2022, the addition of the STI H250 provides customers with a full suite of solar trackers products. STI H250, which upholds Array’s stringent standards for reliability and durability, is designed for sites with irregular boundaries, highly angled blocks or fragmented project areas.

Continue reading

Is the German utility-scale energy storage market set to take off?

A 4.5MWh BESS using Audi EV batteries brought online by RWE in January 2022.. Image: RWE.

Germany’s early lead among Europe’s battery storage adopters is now long gone. But with the urgency to deploy renewable energy compounded by the need for greater energy independence, some industry players and experts see change coming on the horizon in the German market, Cameron Murray writes.

This is an extract of an article which appears in Vol.32 of PV Tech Power, Solar Media’s quarterly technical journal for the downstream solar industry. Every edition includes ‘Storage & Smart Power,’ a dedicated section contributed by the team at Energy-Storage.news.

As by far Europe’s largest economy, the German market is usually on the radar of businesses in any fast-growing and internationalising sector. But when it comes to large-scale front-of-meter battery storage projects, its deployment figures for 2021 lagged far behind the UK, Ireland and France.

The residential sector has conversely always been very strong, as homeowners increasingly seek to back up their home PV systems. But just 32MW of utility-scale (1MW-plus) projects were installed in thecountry in 2021, according to a recent report by a group of RWTH Aachen University-based and spinout organisations.

However, the situation is starting to change, one of its authors tells PV Tech Power.

“The large-scale market is gaining traction, with different drivers from previous years. You have big Innovation Tenders for co-located sites, you have many industrial sites installing MW-plus systemsand you also have the Grid Boosters which will provide a huge boost to the market,” says Jan Figgener, head of grid integration and storage system analysis at ISEA RWTH Aachen University.

People see the German market now as ‘boiling’ and want to be there early, adds Florian Mayr, partner at clean energy finance and strategy consultancy Apricum.

Two companies which were part of the start of the energy storage boom in the UK, investor Gore Street Capital and renewables developer Anesco, entered the German market in quarter one 2022. In June, SwissLife Asset Managers, which has US$290 billion of investments, joined them when it acquired a platform with a 220MW BESS pipeline.

But this bullishness isn’t necessarily widely shared. Claus Urbanke, head of wind and solar Germany for Norwegian hydropower company Statkraft, says that the short-term storage needs of the market arelimited and that Statkraft does not currently see a commercial case for standalone battery energy storage, although it is participating in the Innovation Tenders from federal network operator Bundesnetzagentur for co-location, explained later.

Jorg Blaurock, partner at 3Energie Consulting which produces annual reports on the storage sector for national storage association BVES, agrees to an extent. He says that Germany does not need any moreenergy storage for grid stability as its needs are already well served by existing assets and interconnection with other countries, and that the main driver is opportunities in the wholesale energy market capitalisingon increased volatility.

Where are we today?

One big reason why the German battery energy storage market has not taken off yet is because of a relatively small grid frequency services market, typically the first driver for battery storage because of itsstable revenue guarantees. This relates to Germany’s greater array of options for grid flexibility, including numerous interconnectors to other national grids.

Value stacking is also more difficult due to unfavourable regulatory conditions. This stems from the existing regulatory definitions for storage assets being inadequate according to BVES, although should change going forward after new definitions were brought into German law in May 2022.

Frequency containment reserve (FCR) is the main ancillary service for batteries to play in, but the 550-600MW market is close to saturation with around 600MW of utility-scale battery energy storage installedat the time of writing, according to project developer ECO STOR.

FCR will soon be replaced by aFRR, which will help make the service more international amongst Europe’s interconnected markets, although will not on its own increase the size of the market, points out Statkraft’s Urbanke.

“There was a short time when these (short duration storage) projects were commercially viable in primary reserve (FCR), but since this is such a small segment of the market which got exploited quickly,this opportunity doesn’t exist anymore,” he says.

The period he refers to is around 2018 when nearly 200MW of utility-scale battery storage was installed according to Delta-EE, a record year for the sector. But the market slowed substantially in 2020 and 2021 as FCR was increasingly saturated.

The largest operational battery storage system in Germany today is the Lausitz Battery Energy Storage System at 60MW/52MWh, attached to a coal plant operated by power plant operator andutility LEAG. LEAG, RWE and other large utilities have been the main players installing large systems to-date, says Lars Fallant, COO of project developer Tricera Energy.

These are market-driven projects, he adds, capitalising on grid frequency services and trading opportunities. These, plus the Innovation Tenders incentivising co-located storage projects and a handfulof massive ‘Grid Booster’ storage tenders are the main drivers of the market going forward, according to all the sources we interviewed.

The Smareg
4 project in
Eisenach,
Germany,
developed by
Smart Power and
recently acquired
by BCP Battery. Image: Smart Power.

‘Ukraine has amplified the drivers’: ancillary services and short-term trading

Along with the rest of the European Union, Germany recently upped its renewable energy targets for 2030 to reduce reliance more quickly on Russian fossil fuels after its invasion of Ukraine.

As more renewable resources come onto the German grid, this will increase market volatility which in turn creates an opportunity for battery storage to capitalise in short-term trading markets. Delta-EE anticipates thatthis ramp-up in storage will start in 2025 although the numbers it is expecting are still far below what is needed. It expects around 450MW of additions in 2025 growing (with a dip in 2026) to around 800MW in 2030.

But even before any ramp-up of renewable resource deployment happens – it’s still early days – the existing revenue opportunities for storage have increased substantially, says Georg Gallmetzer, managing director of ECO STOR. And that is despite a revenue source that has historically made up half of the value stack for big batteries no longer being available for projects being commissioned after 2022.

He says that the prices in the auxiliary (ancillary) service markets and spreads in short-term trading have multiplied so much recently that the business model is stronger than last year, even with a 30% increase in material costs due to supply chain constraints (lithium-ion batteries, transformers, concrete and building work etc).

Fallant partially agrees: “The frequency response and energy trading markets have increased recently, but most owners go for frequency response because it ages the battery less quickly because of shallowercycling. But the outlook is that batteries will do more energy trading, although no one knows exactly where the prices will go.

Because growth in energy storage will never keep up with growth in renewables, according to Gallmetzer, opportunities for storage in trading and grid services will continue to increase until the 2030s or2040s when batteries may eventually begin to cannibalise their revenue opportunities.

This is an extract of an article which appears in Vol.32 of PV Tech Power, Solar Media’s quarterly technical journal for the downstream solar industry. Every edition includes ‘Storage & Smart Power,’ a dedicated section contributed by the team at Energy-Storage.news. Subscribe to the journal and read the newest (Q3 2022) edition and all previous issues here.

Continue reading

GameChange Debuts New Terrain-Following Solar Tracker

GameChange Solar has unveiled the terrain-following Genius Tracker TF. This system allows for greater slope change, allowing the tracker system to follow the undulations of the ground. This allows installers to drop construction costs by reducing or eliminating civil grading work as confirmed through real-world testing.

“Customers have been asking for terrain following capabilities for our leading Genius Tracker system,” states Andrew Worden, CEO of GameChange Solar. “Not only have we met their requests, but we have leapfrogged all other tracker companies to give our customers the greatest post to post slope change and other needed topography related allowances in the industry. We feel this can meaningfully reduce grading costs and help our customers improve their project ROIs.”

GameChange Solar is a manufacturer of fixed tilt and tracker solar racking systems, with over 21 GW sold.

Continue reading

Terra-Gen Finances 410 MW Second Phase of California Solar, Energy Storage Facility

Terra-Gen’s EdSan 1A solar project on Edwards Air Force Base in Kern County, Calif.

Independent renewable energy provider Terra-Gen LLC has completed financing on the second phase of its Edwards Sanborn Solar Storage facility in Kern County, Calif.  This phase of the Edwards Sanborn Solar Storage facility is composed of 410 MW AC of nameplate solar capacity (358 MW AC at the point of interconnection) and 1,786 MWh of battery storage.  The first phase of the Edwards Sanborn project was financed in July 2021 and its 345 MW of solar and 1,505 MWh of storage are now fully operational.

The financing for the second phase includes $959 million senior secured credit facilities comprising a $460 million construction and term loan facility, a $403 million tax equity bridge facility, and a $96 million construction and revolving letter of credit facility. U.S. Bank is providing the tax equity commitment for the project, with BNP Paribas, CoBank, ING and Nomura Securities leading the construction and term financing. 

“Consistent with the first phase of the Edwards Sanborn project, the second phase deploys an innovate offtake structure that has been well received in the financing markets and allows us to raise the capital necessary to progress the construction of this transformative project,” says Jim Pagano, Terra-Gen’s CEO. “Once complete, Edwards Sanborn will play a significant role in helping California meet its carbon reduction goals and ensure electricity reliability through the use of stand-alone and collocated energy storage.”

Terra-Gen’s Edwards Sanborn project is located in Kern County on land leased from Edwards Air Force Base as well as on adjacent private land. Mortenson is the full engineering, procurement and construction contractor on both the solar and energy storage scopes with First Solar supplying the solar modules and LG Chem, Samsung and BYD supplying the batteries.

Terra-Gen expects the solar portion of the second phase to come on-line in the third and fourth quarters of 2022 with the battery storage scheduled to be fully operational by the third quarter of 2023. Terra-Gen is advancing development on future phases of this project that will include over 2,000 MW of incremental solar and energy storage to be interconnected to the CAISO grid. Subsequent phases will begin to be financed in 2023 and begin to come on-line in 2024.

Continue reading

Greenbacker Closes $186 Million Credit Agreement Covering Two 80 MW Solar Farms

Another Greenbacker Renewable Energy Co. LLC solar project in Washington

Greenbacker Renewable Energy Co. LLC (GREC), a green energy investment company and independent power producer, has entered into a senior credit agreement of $186.2 million with KeyBank N.A. and Fifth Third Bank. KeyBank served as administrative agent for the lenders, and KeyBanc Capital Markets and Fifth Third Bank, National Association served as joint lead arrangers.

The transaction is one of Greenbacker’s largest standalone debt financings to date, providing a construction loan facility to build two of the biggest solar projects in company history.

The MTSun and Fall River solar farms – which make up GREC’s Ponderosa portfolio – are each 80 MW AC. Both assets have long-term power purchase agreements in place with local investment-grade utilities, MTSun with Northwestern Energy and Fall River with Black Hills Power Inc.

“We’re thrilled to partner with KeyBank and Fifth Third Bank on this senior credit agreement to build projects that will drive a clean energy future in a very real way,” says Spencer Mash, CFO of GREC. “Once complete, they’ll deliver cheaper renewable energy to tens of thousands of households across Montana and South Dakota.”

“The Ponderosa transaction illustrates our ongoing commitment to grow the renewable energy industry by deploying capital in high-quality assets,” states Gregory Berman, director of Utilities Power & Renewables at KeyBanc Capital Markets. “This represents our seventh financing with Greenbacker, and we look forward to supporting their continued growth as a leader in the energy transition.”

The two assets are located in Yellowstone County, Mont. and Fall River County, S.D., respectively.

“Fifth Third Bank’s commitment to financing renewable energy technologies is well-known and steadfast,” comments Kyle Kuhn, renewable energy executive director at Fifth Third Bank. “We are pleased to be a part of this milestone transaction with Greenbacker that will support the clean energy transition.”

Continue reading